Stop notice in planning
A stop notice is an enforcement notice that can be issued by a local planning authority if they believe there is a breach of planning control, that is, where development is carried out without the proper planning permission, or where there is a failure to comply with a condition or limitation stipulated on permitted development rights.
It is an order for the ‘relevant activity’ to cease on any part of that land to which the notice relates.
Section 183 of the Town and Country Planning Act 1990 enables the local planning authority to serve a stop notice either alongside the serving of an enforcement notice, or afterwards. If the compliance period specified in the enforcement notice has expired, and the relevant activity continues, then a stop notice can be issued.
A stop notice can be withdrawn at any time by giving notification to those who were served with the notice. (This does not prejudice the authority’s power to serve another stop notice.)
If more immediate action is required, the local authority can issue a temporary stop notice.
Failure to comply with a stop notice can lead to prosecution and an unlimited fine.
[edit] Related articles on Designing Buildings Wiki
- Enforcement notice.
- Local planning authority.
- Permitted development.
- Planning appeal.
- Planning enforcement.
- Planning enforcement officer
- Planning objection.
- Planning permission.
- Regularisation.
- Special Nature Conservation Order SNCO.
- Stop work order.
- Temporary stop notice.
- Town and Country Planning Act
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.